Restoration - Autumn 2004 - 2005
Tower Work Sep 04  

Tower Work Oct 04 

Tower Work Nov 04 

Tower Work Jan 2005

Tower Work late Jan 2005 

Tower Work Feb 2005 

Porch Work Mar 2005

Porch Work May 2005

Completion 2005

Views from Scaffolding 2004

 

Scaffolding erected round the towerThe Restoration Works started at the end of August 2004 when the scaffolding was erected around the Tower. The work was to have lasted approximately 3 months and consisted mainly of work to the outside of the tower. A delay with the weather, amongst other things, lengthened the job to 6 months. The cost to the church, however, remained the same. The roof tiles were stripped, new felt laid and the tiles replaced. The guttering and down-pipes were renewed and the drainage at the base of the tower improved. The pointing to the outside of the tower was of sand and cement, a non porous substance. This type of mortar doesn't allow the tower to 'breathe' moisture from its walls, so this is why the tower was damp. This pointing was stripped off and replaced with traditional lime mortar. Also, there were voids (pockets) in the walls which allowed water to ingress and track down to the inside of the tower. These were rebuilt or filled with grout. The porch was renovated, with new external doors and the window feramenta (iron-work) reconditioned. The windows were blanked off while they were taken away to be worked on. The poor stonework was renewed and woodwork was stripped back and repainted.